Benchmarking Cost Overruns in Transportation Infrastructure Investments

Authors

  • Alolote Ibim Amadi Department of Quantity Surveying, Rivers State University, P.M.B 5080, Port Harcourt, Nigeria
  • Amadi Kelvin Chijioke

Keywords:

Accuracy, Conceptual Estimates, Cost Overruns, Project Phases, Highway Projects

Abstract

Highway projects have historically experienced significant cost overruns, with front end implications for the sustainability of transportation investments. However, the criteria for assessing cost overruns continues to elicit diverse opinions and has become a debatable issue in the literature. Some studies allude to detailed design stage estimates, while others tag conceptual stage estimates, as the ideal benchmark for quantifying the project cost deviations. A survey of the literature, principally from scholarly articles and the technical press is carried out. This is with a view to identify popular opinion on the phase of development, which should ideally constitute the basis for assessing cost overruns in transportation investment. This study weighs and evaluates the literature arguments. The findings show that there is no uniform nomenclature in the literature for labeling the phases of development and that different terminologies are evident. However, the majority of the literature arguments favour the ‘decision to build’ stage. The study espouses benchmarking cost overruns at the ‘decision to build’ stage to provide a sustainable platform for assessing the viability of transportation infrastructure Investments.

Keywords: Accuracy of Estimates, Conceptual Estimates, Cost Overruns, Development Phases, Highway Projects.

Author Biography

  • Alolote Ibim Amadi, Department of Quantity Surveying, Rivers State University, P.M.B 5080, Port Harcourt, Nigeria

    Dr Alolote. I. Amadi holds a PhD in Construction Management from the University of  Salford. (UK), completing the thesis " Explaining Cost Overruns in Highway Projects: Geo-spatial Regression Modelling and Cognitive Mapping of Latent Pathogens and Contextual Drivers. ". Alolote also holds an M.Phil. (with distinction) in Environmental Management in addition to a B.Tech (Hons, First Class) in Quantity Surveying from The Rivers State University, Nigeria.

    Alolote is Lecturer of Quantity Surveying, Construction, Project and Environmental Management at the Rivers State University, Nigeria (2006 - 2020). Alolote is a  chattered Member of the Nigerian Institute of Quantity Surveyors and is registered with the Quantity Surveyors Registration Board of Nigeria. Alolote has published over 30 research articles and book chapters and is a reviewer for several international journals.  

     

References

Africa Infrastructure Country Diagnostic. (2008). Roads in Sub-Saharan Africa. World Bank Report

Alavi, S.A. and Tavares, P.E. (2009). Highway project cost estimating and management. The State of Montana Department of Transportation, Final Report.

Anderson, S., Molenaar, K., and Schexnayder, C. (2006). “Guidance for cost estimation and management for highway projects during planning, programming, and preconstruction.” Final Report 574, National Cooperative Highway Research Program (NCHRP), Washington, DC.

Asmar, S.M., Mounir, El., Awad, S., Hanna, F., Gary C, and Whited, M. (2011). New Approach to Developing Conceptual Cost Estimates for Highway Projects. American Society of Civil Engineers.

Bordat, C., B. G. McCullouch., S. Labi, and K. C. Sinha. (2004). An Analysis of Cost Overruns and Time Delays of INDOT Projects. Joint Transportation Research Program, Indiana Department of Transportation

Cantarelli, C.C., Flyvbjerg, B., Molin, E.J.E and Van Wee, B. (2010). Cost Overruns in Large-scale Transportation Infrastructure Projects: Explanations and Their Theoretical Embeddedness. EJTIR 10(1), pp. 5-18. March,

Chou, J. (2005). Item-level quantity-based preliminary cost estimating system for highway earthwork, landscape, subgrade treatments, base, surface courses, pavement and traffic control. Doctoral dissertation presented to the faculty of the graduate school of the University of Texas at Austin

Creedy. G.D. (2006). Risk Factors leading to cost overruns in the delivery of highway construction projects. An unpublished PHD thesis submitted to the Queensland University of Technology.

Donnell, k. E. (2005). Identification of potential strategies, methods, and tools for improving cost estimating practices for highways. An unpublished Masters dissertation. The Office of Graduate Studies of Texas A&M University

Evans and Peck, (2008). Best practice cost estimation for publicly funded road and rail construction. Department of Infrastructure, Transport, Regional Development and Local Government, Australia.

Flyvbjerg, B Holm, Mette Skamris., and Buhl, Søren. (2002). Underestimating costs in public works projects: error or lie?. Journal of the American Planning Association, vol. 68, no. 3, pp. 279-295.

Hall, P. (1980). Great Planning Disasters. Penguin Books, Harmondsworth.

Mahamid, I (2011) Early cost estimating for road construction projects using multiple regression techniques, Australasian Journal of Construction Economics and Building, 11 (4) 87-101

Odeck, J. (2004). Cost overruns in road construction: What are their sizes and determinants?. Norway Journal of Transport Policy (11) 43–53

Ogunlana, S. O. (1989). Accuracy in design cost estimating. A Doctoral Thesis submitted at Loughborough University of Technology.

Phaobunjong, k. (2002). Parametric cost estimating model for conceptual cost estimating of building construction projects. An unpublished PhD thesis, Faculty of the Graduate School, The University of Texas,

Sabol, L. (2008) Challenges in cost estimating with building information modeling. Design and Construction Strategies. Washington, DC . pp.202- 222

Schexnayder, C ., Sandra L. W and Christine, F.( 2003). Project cost estimating a synthesis of highway practice. American Association of State Highway and Transportation Officials (AASHTO)

Simon, J. (1991). Let’s make forecast and actual comparisons fair. TR News, 156,6-9.

Steven M, T. and Oberlender, G. (2003). Predicting accuracy of early cost estimates using factor Analysis and multivariate regression. Journal of Construction Engineering and Management. American Society of Civil Engineers (ASCE). pp198 -204

Tan, F and Makwasha T. (2010). Best practice’ cost estimation in land transport infrastructure projects. Australasian Transport Research Forum Proceedings. Canberra, Australia.

The Association for the Advancement of Cost Engineering, AACE. (1997). Cost Estimate Classification System, Recommended Practice No. 17R-97:

The Department of Energy, DOE, Guide. (2011). Program and Project Management for the Acquisition of Capital Assets, dated U.S. Department of Energy Washington, D.C. 20585 11-29-10

The United States Government Accountability Office, GAO. (2009). Cost Estimating and Assessment Guide, Best Practices for Developing and Managing Capital Program Costs, GAO-09-3SP. Washington, D.C

Turochy, R. E., Lester A. H., Lacy, L. A. and Robert S. D. (2001). Highway project cost estimating methods used in the planning stage of project development. Technical Assistance Report, Virginia Transportation Research Council

Wachs, M. (1989). When planners lie with numbers. Journal of the American Planning Association, 55(4), 476-479.